Date | Project Schedule |
---|---|
Q4 2016 | Geotechnical Studies at Kinosis project site |
Q1 & Q2 2017 | Environmental Field Studies at Kinosis project site Alberta Environment & Parks Public Land Acquisition Application Alberta Consultation Office guidance on Indigenous Consultation |
Q3 2018 | Submit Approval Application to Alberta Environment & Parks Submit Development Permit Application to RMWB Stakeholder Engagement & Project Open House |
Q3 2019 | Construction is estimated to start within 1 year after approval is received from AEP for Provincial Environmental Approval and Land Acquisition as well as RMWB for Municipal Development and Building Permits |
Q3 2020 | Mechanical Completion |
Q4 2020 | Startup & Commissioning |